Build a House PERT Chart

Build a House PERT Chart

PERT Chart - Build a House

1

2

3

4

5

7

6

8

9

11

10

Dig Ground

6 days

Lay Foundation

11 days

Frame House

21 days

Install

Windows

4 days

Put in Rough Plumbing and Electric

9 days

Install

Roof

3 days

Install Sheetrock

4 days

Paint Walls

3 days

Install Flooring

2 days

Install

Exterior

11 days

Install Interior (doors, applicances, etc.)

3 days

4

49
0
2
publish time: 2020-09-11
lizzie

You can use this PERT chart example to gauge the minimum time necessary to build a house so that you can analyze the connections between tasks and predict risks. Duplicate this example into your own EdrawMax and create your own PERT chart based on your projects.