Forward Pass Calculation Precedence Diagram
Use immediately

Forward Pass Calculation Precedence Diagram

0

A

7

7

7

C

17

10

17

D

29

12

29

G

35

6

39

H

50

11

50

I

63

13

7

B

22

15

22

F

39

17

FORWARD PASS CALCULATION

15
0
0
publish time: 2021-02-26
Lisa Anderson

Forward Pass Calculations in Precedence Diagram Method (PDM), determine the minimum dates at which each construction activity can be performed and, ultimately, the minimum duration of a construction project. Forward pass is a technique to move forward through network diagram to determining project duration and finding the critical path or Free Float of the project.