Pay
Float Calculation Precedence Diagram

Float Calculation Precedence Diagram

0

A

7

0

7

7

7

C

17

17

27

10

17

D

29

27

37

12

29

G

35

44

50

6

39

H

50

39

50

11

50

I

63

50

63

13

7

B

22

7

22

15

22

F

39

22

39

17

Float Calculation

Float : 0

Float : 10

Float : 10

Float : 0

Float : 0

Float : 15

Float : 0

Float : 0

2
0
0
publish time: 2021-02-26
Lisa Anderson

Float values indicate how much each individual activity can be delayed before affecting successor activities or the planned project completion date. In Precedence Diagram Method (PDM), Total Float shows the difference between the Earliest Start (ES) and Latest Start (LS) of an activity before the completion date is delayed.