Project Construction Schedule
Use immediately

Project Construction Schedule

Serial number

Main construction projects

2020/5/1

2020/7/1

2020/10/1

2020/5/1

2020/6/1

2020/7/1

2020/8/1

2020/9/1

2020/10/1

1

Reinforced tunnel foundation

2

Backfill

3

scaffold

4

Reinforced Column

5

Ribbed floor

6

Brick wall

7

Roofing works

8

Aluminum alloy window (system, installation)

9

Internal and external wall plastering, coating

10

Cement mortar floor

11

Stair rails and handrails

12

bathroom

13

Septic tank

14

underground drain

15

Sporadic Engineering

16

XXX

17

XXX

18

XXX

19

XXX

Production unit:

Project Construction Schedule

Planned start date: May 5, 2020 Planned completion date: September 30, 2020 Total construction period: 149 days

226
4
5
publish time: 2021-03-04
Charlotte

The picture is a Gantt chart of project construction progress. The project spans 5 months and has a total of 149 days, including surveying, artificial leveling site; backfilling; scaffolding; roofing engineering and other 20 construction projects. The start date is May 5 and the completion date is September 30, as shown in the figure. Show.