System Assessment PERT Chart
Use immediately

System Assessment PERT Chart

PERT Chart

1

2

4

3

6

5

7

1

2

3

4

5

6

7

Assessment of Current System

Start Day: Day 1

End Day: Day 2

Obtaining required hardware

Start Day: Day 6

End Day: Day 7

Setting up Excel CRM Database

Start Day: Day 8

End Day: Day 10

Assessment of New System

Start Day: Day 5

End Day: Day 6

Planning of New System

Start Day: Day 2

End Day: Day 5

Setting up Required Software and OS on the Hardware

Start Day: Day 7

End Day: Day 8

Excel CRM Database Deployment

Start Day: Day 10

End Day: Day 11

Duration: 1 Day

Duration: 3 Days

Duration: 1 Day

Duration: 1 Day

Duration: 1 Day

Duration: 2 Days

Duration: 1 Day

31
0
1
publish time: 2021-04-26
Alex Mac

Here is a PERT chart about the system assessment. PERT is the short form of “Program Evaluation Review Technique”. A PERT chart is a statistical chart used for project management to analyze and represent the different tasks in a project. Learn more details from this PERT chart, or try to make yours for your project.