Software Release PERT Chart
Use immediately

Software Release PERT Chart

Design hardware

12 Oct

2021

4 wks

9 Nov

2021

Breadboard

hardware

9 Nov

2021

2 wks

23 Nov

2021

Design Software

12 Oct

2021

6 wks

23 Nov

2021

Test hardware

23 Nov

2021

3 wks

14 Dec

2021

Release hardware

14 Dec

2021

2 wks

28 Dec

2022

Manufacture

hardware

28 Dec

2021

4 wks

25 Jan

2022

Formalize Specs

1 Sep

2021

6 wks

12 Oct

2021

Complete Software

14 Dec

2021

4 wks

11 Jan

2022

Release Software

11 Jan

2021

1 wks

18 Jan

2022

Layout manual

12 Oct

2021

3 wks

2 Nov

2021

Finish manual

2 Nov

2021

4 wks

30 Nov

2021

Relesae manual

30 Nov

2021

1 wks

7 Dec

2021

Print manuals

7 Dec

2021

4 wks

4 Jan

2022

Start

1 Sep 2021

Finish

25 Jan 2022

9
0
0
publish time: 2021-05-20
Charlotte

A software release PERT chart allows managers or HODs to evaluate the time and resources necessary to manage a project. This evaluation includes the ability to track required assets during any stage of production in the course of the entire project. As per the image, a software release PERT chart incorporates data and information from multiple departments like designing, acquiring hardware, releasing test manuals, and completing the software before the release. As the software release diagram suggests, a PERT chart enables you to create milestones for your project. During the time between each milestone, one can use the chart to identify any possible outcomes or obstacles that a project may face. It means one can quickly address them, or prepare for them, to help a project stay on track.