Designed with EdrawMax, this template is a PERT (Program Evaluation and Review Technique) chart for the Cortex AI project visualizing its timeline, task dependencies, and critical path with tasks including Project initiation, role assignment, and research (Weeks 1–2); Finalize website layout and appearance (Weeks 3–4); Develop basic website functionalities (Weeks 5–7); Create communication style guide and integrate Simulate AI (Weeks 5–8); Build AI-powered testing functionality (Week 8); Final development, testing, and presentation (Weeks 8–9); Comprehensive testing (Week 9); Quality check, documentation, and submission (Week 9), dependencies shown via arrows indicating task sequences like Task 3 depending on Task 2, and the critical path being the longest path (Tasks 1→2→3→6→8) determining the minimum project duration of 9 weeks to aid in identifying critical tasks, resource allocation, and potential bottlenecks for keeping the project on schedule.